One in six tenders awarded issue raises infrastructure risks
Video · Brightcove player not connected in this prototype
The government agency Infrastructure South Africa (ISA) has raised the alarm about the low rate of tenders awarded in 2025, as opposed to the number that were advertised.
In Parliament on Tuesday, ISA acting head Simphiwe Ndlovu told the Select Committee on Public Infrastructure that recent analysis showed that more than 70% of the total number of advertised tenders had been either cancelled or closed.
Ndlovu revealed that in 2025, 2 549 tenders were advertised, of which only 16.98% were awarded.
ISA said Eskom had cancelled 159 tenders, followed closely by the Passenger Rail Agency of SA (PRASA) with 150, and Transnet with 129, as Engineering News reports.
Other entities with significant cancellation figures included the Department of Water and Sanitation, the Road Accident Fund (RAF) and Public Works.
Stephen Grootes discusses the issue with Dean Macpherson, Minister of Public Works and Infrastructure.
Macpherson remarks that the "shocking" figures are due to a number of reasons, none of which he says are acceptable.
"This includes tenders that are cancelled, that are not correctly packaged together as they should be. In fairness, there's also an element when they are valuated, that they are in such a poor state that they actually cannot be awarded."
RELATED: Can Ramaphosa's R1 trillion infrastructure plan create jobs for SA youth?
He refers to the Stats SA conclusion in the GDP figures for the first quarter, that fixed capital investment in infrastructure continues to decline despite a record budget being allocated.
This speaks to what they've seen across government departments, the Minister says, which is that the issue is no longer money but implementation.
"The issue is now being able to actually get those projects and tenders off the ground... That is why we put R600 million aside over the next five years to do the project preparation for ourselves to try and mitigate the cancellation of tenders due to nonresponsiveness or poor tender documentation."
"Of course we can't do that for the 2 500 affected tenders because some of those come from SOEs, other departments and spheres of governemt, but it is something quite extraordinary that is not going to help us turn the tide on infrastructure backlogs if we're not able to get them awarded correctly."
The Minister raises the apparent need for centralisation and standardisation to some extent in tender procurement to get things moving.
"I appreciate that the Public Finance Management Act is there to protect public money, but if we also do have a serious infrastructure crisis it can't be business as usual... and if we have a differentiated approach, that creates different problems."
He also highlights a need for stronger public–private partnerships and dedicated specialists to help expedite tender allocation.
Scroll up to the audio player to listen to the interview with the Minister of Public Works and Infrastructure