Joburg City Power has thanked residents in the Johannesburg CBD for their patience after going weeks without electricity.
Large parts of the inner city have been without power since September, following several separate incidents involving fires and explosions at the central substation.
ALSO READ:
City Power targets midday restoration for Marshalltown substation following fourth fire in a month
City Power faces delays in restoring power to Marshalltown
The power utility said that electricity has now been restored to 98% of affected residents in the CBD, with the remaining areas expected to be reconnected soon.
City Power spokesperson Isaac Mangena has urged residents who are still without electricity to remain patient as restoration efforts continue.
"Customers whose electricity supply has been restored are advised to wait 15 to 30 minutes before switching on or plugging in appliances. Appliances should then be switched on gradually to avoid a sudden increase in electricity demand, which could place pressure on the network and cause further interruptions," said Mangena.