Johannesburg City Power says electricity supply to parts of the central business district should be restored by Monday 5 October.
Large parts of the inner city have been without power throughout September, with supply yet to be fully restored.
The outage was caused by a fire at the Central Substation, which is suspected to have been ignited during a cable theft incident.
City Power spokesperson Isaac Mangena says technicians are working around the clock to restore supply.
"Power supply has now been restored to Carlton Centre and Standard Bank, while supply to Selby has also been restored through an alternative route. This progress follows the successful testing of repaired cables and equipment. The critical cables supplying Carlton Centre and Standard Bank have been successfully tested, cleared and returned to service," said Mangena.