The Public Protector has found that feasibility studies costing R46 million for the Moloto Rail Corridor Development Project were above board.

A group of concerned residents lodged a complaint, alleging the project was unduly delayed for over 20 years and that funds were misused.

The project was for the implementation of the rail and the expansion of the road on Moloto Road.

After millions spent on the studies, the rail project has still not been implemented.

However, the Public Protector, Kholeka Gcaleka, has found that the studies were procedurally compliant with the Public Finance Management Act.

“The combined expenditure of approximately R46 million was not fruitless or wasteful, as each study served a distinct purpose under different funding models. The second feasibility study broadened the scope to include multiple transport-oriented development options, which informed the subsequent decision to prioritise road upgrades.

“The upgrades have since transformed the Moloto Corridor into a safer, modern route, substantially achieving the project’s objectives.”