While City Power raises the alarm about alleged targeting of infrastructure, a local think-tank has placed maintenance backlogs at more than R44 bn.

The Centre for Development and Enterprise (CDE) has called for stronger management to help keep the lights on.

ALSO READ:

City Power worried about repeated attempts of electricity infrastructure vandalism, theft

City Power says it can’t confirm restoration of electricity supply in Joburg CBD

Their report, Powering Joburg’s Turnaround, was released this week.

Several regions around Joburg have been without electricity since Saturday, reportedly caused by a substation fire.

The incident occurred a day after power was restored following a two-week outage.

The CDE’s report found that ageing and deteriorating infrastructure accounts for 60% of the city’s power outages, with illegal connections, theft and vandalism adding pressure.

The centre is calling for experienced leadership and critical technical vacancies to be filled, along with improving meter systems to avoid billing failures.

Researchers hope these issues will be among top priorities for the next administration.