Johannesburg officials are set to conduct an oversight visit to the damaged Lillian Ngoyi Street in the city’s CBD.

This follows delays to the street's rehabilitation project.

ALSO READ:

Three years later, Lilian Ngoyi Street is still not finished

CoJ to start phase 2 of Lilian Ngoyi Street construction project in CBD

Lilian Ngoyi Street reopens to traffic

In 2023, parts of Bree Street, as it was popularly known, were damaged in an explosion.

The Johannesburg Roads Agency (JRA) had set itself a deadline of late August to finish the outstanding work.

For more than three years, Lillian Ngoyi Street has been a work in progress.

The plan was to repair and restore the affected sections of the road, with the project eventually divided into phases.

Phase one was completed in September 2025. That included work on the initial section, beautification and the partial opening of the road.

However, the remaining 1.8 kilometres have proved far more difficult to complete.

The city has blamed cash-flow problems and operational challenges for the delays.

There is another issue putting the project under the microscope: roughly 80% of the project's budget has already been spent, yet the work remains unfinished.

The project has already gone through two contractors, raising questions about procurement, project management and whether the original timelines and budgets were realistic in the first place.