Eskom has warned that transferring its transmission grid too soon could undermine the utility’s finances and unsettle investors.
This comes as South Africa’s electricity market reforms gain momentum.
ALSO READ:
Eskom targets 2027 to end load reduction nationwide
700 Eskom transformers failing due to vandalism and illegal connections
Eskom said it supports government plans to create an independent transmission system operator but wants the transfer of its transmission assets delayed until key financial risks are resolved.
Eskom board chairperson Mteto Nyati said moving the grid into a separate company too early could trigger change-of-control clauses in loan agreements, create accounting complications, and unsettle bondholders.
The utility argues that the new operator should first function independently before ownership of transmission assets is transferred.
The reforms are central to opening South Africa’s electricity market to greater competition and improving grid access for independent power producers.
However, Eskom insists the transition must be carefully sequenced to protect its financial stability and maintain lender confidence.