The KwaZulu-Natal Department of Public Works and Infrastructure has halted the awarding of a R7 billion construction project after flagging irregularities in the tender process.
The tender was awarded during the previous administration, and work was set to begin soon for the construction of a government precinct building.
The structure is earmarked to house all government departments in one building to save money used to rent property.
MEC Martin Meyer has taken the legal route to stop the project.
The department said the high hopes for the project, worth billions of rand of taxpayers’ money, have been met with challenges.
Meyer approached the Durban High Court, which found that the tender was awarded illegally.
This resulted in the court setting aside the awarding of the tender.
Department spokesperson Steve Bhengu said, “The ruling now allows the department to proceed with a fresh and lawful procurement process for the government precinct, ensuring the project continues on sound legal footing and in the public interest.”
The department said it will stick to its promise to get rid of corruption within its ranks.