The Public Protector has found that systemic failures by both the Gauteng Department of Health and the Department of Infrastructure Development directly contributed to major delays in repairing the Charlotte Maxeke Academic Hospital following a devastating fire in 2021.

Public Protector Kholeka Gcaleka released the investigation's findings in Tshwane on Friday, following a comprehensive probe into the state's administrative response to the blaze.

The report revealed that both departments failed to effectively use allocated funds and did not comply with established infrastructure delivery frameworks, which further derailed the repair project.

Furthermore, poor communication between the two entities resulted in persistent disputes, causing the project to later be transferred from Infrastructure to Health, a bureaucratic shift that triggered even more delays.

Alarmingly, the investigation also uncovered that the hospital did not fully comply with critical fire and building safety requirements, citing a lack of adequate fire detection systems, clear exit plans, and other standard safety measures.

Financially, while more than R426 million was initially allocated to get the facility back to full capacity, only R139 million has been spent so far.

Gcaleka highlighted the administrative breakdown that crippled the recovery efforts.

"Evidence further reveals that there were ineffective co-ordination and planning between the two departments which resulted [in] persistent disputes and disagreements concerning the scope, budget and processes," Gcaleka said.

The total cost of repairs is now expected to exceed R1.7 billion, leaving the government to look to both the state and the private sector for additional funding to bridge the massive financial shortfall.